An industrial client of ours came to us with a common concern. They were adding a pipe run to a very congested boiler room and wanted to reduce shutdown time and in-the-field modifications. By leveraging our scanning and modeling ability, our client got the data they needed to design and prefabricate the pipe and completely pre-plan the installation process. This workflow allowed them to achieve the installation with only one field weld. It also greatly reduced the shutdown time associated with the project.